Practice Test Free
  • QUESTIONS
  • COURSES
    • CCNA
    • Cisco Enterprise Core
    • VMware vSphere: Install, Configure, Manage
  • CERTIFICATES
No Result
View All Result
  • Login
  • Register
Quesions Library
  • Cisco
    • 200-301
    • 200-901
      • Multiple Choice
      • Drag Drop
    • 350-401
      • Multiple Choice
      • Drag Drop
    • 350-701
    • 300-410
      • Multiple Choice
      • Drag Drop
    • 300-415
      • Multiple Choice
      • Drag Drop
    • 300-425
    • Others
  • AWS
    • CLF-C02
    • SAA-C03
    • SAP-C02
    • ANS-C01
    • Others
  • Microsoft
    • AZ-104
    • AZ-204
    • AZ-305
    • AZ-900
    • AI-900
    • SC-900
    • Others
  • CompTIA
    • SY0-601
    • N10-008
    • 220-1101
    • 220-1102
    • Others
  • Google
    • Associate Cloud Engineer
    • Professional Cloud Architect
    • Professional Cloud DevOps Engineer
    • Others
  • ISACA
    • CISM
    • CRIS
    • Others
  • LPI
    • 101-500
    • 102-500
    • 201-450
    • 202-450
  • Fortinet
    • NSE4_FGT-7.2
  • VMware
  • >>
    • Juniper
    • EC-Council
      • 312-50v12
    • ISC
      • CISSP
    • PMI
      • PMP
    • Palo Alto Networks
    • RedHat
    • Oracle
    • GIAC
    • F5
    • ITILF
    • Salesforce
Contribute
Practice Test Free
  • QUESTIONS
  • COURSES
    • CCNA
    • Cisco Enterprise Core
    • VMware vSphere: Install, Configure, Manage
  • CERTIFICATES
No Result
View All Result
Practice Test Free
No Result
View All Result
Home Practice Exam Free

ITILF Practice Exam Free

Table of Contents

Toggle
  • ITILF Practice Exam Free – 50 Questions to Simulate the Real Exam
  • Free Access Full ITILF Practice Exam Free

ITILF Practice Exam Free – 50 Questions to Simulate the Real Exam

Are you getting ready for the ITILF certification? Take your preparation to the next level with our ITILF Practice Exam Free – a carefully designed set of 50 realistic exam-style questions to help you evaluate your knowledge and boost your confidence.

Using a ITILF practice exam free is one of the best ways to:

  • Experience the format and difficulty of the real exam
  • Identify your strengths and focus on weak areas
  • Improve your test-taking speed and accuracy

Below, you will find 50 realistic ITILF practice exam free questions covering key exam topics. Each question reflects the structure and challenge of the actual exam.

Question 1

Which stage of the service lifecycle is MOST concerned with de ning policies and objectives?

A. Service design

B. Service transition

C. Continual service improvement

D. Service operation

 


Correct Answer: A

Question 2

Which of the following would be defined as part of every process?
(1) Roles
(2) Activities
(3) Functions
(4) Responsibilities

A. 1 and 3 only

B. All of the above

C. 2 and 4 only

D. 1, 2 and 4 only

 


Correct Answer: D

Question 3

What are the categories of event described in the ITIL service operation book?

A. Informational, scheduled, normal

B. Scheduled, unscheduled, emergency

C. Informational, warning, exception

D. Warning, reactive, proactive

 


Correct Answer: C

Question 4

In which of the following situations should a Problem Record be created?

A. An event indicates that a redundant network segment has failed but it has not impacted any users

B. An Incident is passed to second-level support

C. A Technical Management team identifies a permanent resolution to a number of recurring Incidents

D. Incident Management has found a workaround but needs some assistance in implementing it

 


Correct Answer: C

Question 5

Which process is responsible for low risk, frequently occurring, low cost changes?

A. Demand management

B. Incident management

C. Release and deployment management

D. Request fulfillment

 


Correct Answer: D

Question 6

Which list includes information that would be collected when any incident is first logged?

A. Unique reference number, escalation activity, incident priority

B. Unique reference number, incident priority, description of symptoms

C. Escalation activity, closure category, resolution date and time

D. Closure category, description of symptoms, resolution date and time

 


Correct Answer: B

Question 7

A single Release unit, or a structured set of Release units can be defined within:

A. The RACI Model

B. A Release Package

C. A Request Model

D. The Plan, Do, Check, Act (PDCA) cycle

 


Correct Answer: B

Question 8

What is the result of carrying out an activity, following a process or delivering an IT service known as?

A. Outcome

B. Incident

C. Change

D. Problem
xplanation:
Explanation:

 


Correct Answer: E

Question 9

Understanding what to measure and why it is being measured are key contributors to which part of the Service Lifecycle?

A. Service Strategy

B. Continual Service Improvement

C. Service Operation

D. Service Design

 


Correct Answer: B

Question 10

Which one of the following is NOT an aim of the change management process?

A. To ensure the impact of changes are understood

B. To ensure that changes are recorded and evaluated

C. To ensure that all changes to configuration items (CIs) are recorded in the configuration management system (CMS)

D. To deliver and manage IT services at agreed levels to business users

 


Correct Answer: D

Question 11

Which of the following types of service should be included in the scope of service portfolio management?
1. Those planned to be delivered
2. Those being delivered
3. Those that have been withdrawn from service

A. 1 and 3 only

B. All of the above

C. 1 and 2 only

D. 2 and 3 only

 


Correct Answer: B

Question 12

Which one of the following includes four stages called Plan, Do, Check and Act?

A. The Deming Cycle

B. The continual service improvement approach

C. The seven-step improvement process

D. The service lifecycle

 


Correct Answer: A

Question 13

Which stage of service lifecycle has the purpose of aligning IT services with the changing business needs by identifying improvements to IT services?

A. Continual service improvement

B. Service operation

C. Service strategy

D. Service design

 


Correct Answer: A

Question 14

Which of the following combinations covers all the roles in Service Asset and configuration Management?

A. configuration Administrator/Librarian; configuration Manager; Service Desk Manager; configuration Analyst; CMS/tools Administrator

B. configuration Administrator/Librarian; Service Asset Manager; configuration Manager; configuration Analyst; configuration control board; CMS/tools Administrator

C. configuration Manager; configuration Analyst; CMS/tools Administrator; Librarian; Change Manager

D. configuration Administrator/Librarian; configuration Manager; configuration Analyst; configuration control board; CMS/tools Administrator; Financial Asset

 


Correct Answer: B

Question 15

Which of the following are types of service defined in ITIL?
1. Enabling
2. Core
3. Enhancing
4. Computer

A. 1, 3 and 4 only

B. 2, 3 and 4 only

C. 1, 2 and 4 only

D. 1, 2 and 3 only
eferences:
References:

 


Correct Answer: R

Question 16

Which service catalogue view is considered beneficial when constructing relationship between services, SLAs, OLAs, and other underpinning agreements?

A. Service-based SLA view

B. Wholesale customer view

C. Retail customer view

D. Supporting services view

 


Correct Answer: D

Question 17

Which one of the following do major incidents require?

A. Separate procedures

B. Less urgency

C. Longer timescales

D. Less documentation

 


Correct Answer: A

Question 18

Service design emphasizes the importance of the "Four Ps". These "Four Ps" include Partners, People, Processes and one other "P". Which of the following is the additional "P"?

A. Pro t

B. Preparation

C. Products

D. Potential

 


Correct Answer: C

Question 19

Which of the following is NOT a purpose of Service Transition?

A. To ensure that a service can be managed, operated and supported

B. To provide training and certi cation in project management

C. To provide quality knowledge of Change, Release and Deployment Management

D. To plan and manage the capacity and resource requirements to manage a release

 


Correct Answer: B

Question 20

Check, Act and Plan are three of the stages of the Deming Cycle. Which is the fourth?

A. Do

B. Perform

C. Implement

D. Measure

 


Correct Answer: A

Question 21

Which of these recommendations is best practice for service level management?
1. Include legal terminology in service level agreements (SLAs)
2. It is NOT necessary to be able to measure all the targets in an SLA

A. 1 only

B. 2only

C. Both of the above

D. Neither of the above

 


Correct Answer: D

Question 22

Ensuring that the con dentiality, integrity and availability of the services are maintained to the levels agreed on the Service Level Agreement (SLA) is the responsibility of which role?

A. The Service Level Manager

B. The configuration Manager

C. The Change Manager

D. The Information Security Manager

 


Correct Answer: D

Question 23

What is the pre-authorized change known as?

A. A normal change

B. A retrospective change

C. A standard change

D. An ordinary change

 


Correct Answer: C

Question 24

At which stage of the service lifecycle should the processes necessary to operate a new service be defined?

A. Service design: Design the processes

B. Service strategy: Develop the offerings

C. Service transition: Plan and prepare for deployment

D. Service operation: IT operations management

 


Correct Answer: A

Question 25

Which function or process would provide staff to monitor events in an operations bridge?

A. Technical management

B. IT operations management

C. Request fulfillment

D. Applications management

 


Correct Answer: B

Question 26

An incident is proving difficult to resolve. A technician informs their manager that more resource is needed to restore the service.
What has taken place?

A. A functional escalation

B. A service level escalation

C. An incident resolution

D. A hierarchic escalation

 


Correct Answer: D

Question 27

What is the primary focus of business capacity management?

A. Management, control and prediction of the performance, utilization and capacity of individual elements of IT technology

B. Review of all capacity supplier agreements and underpinning contracts with supplier management

C. Management, control and prediction of the end-to-end performance and capacity of the live, operational IT services

D. Future business requirements for IT services are quanti ed, designed, planned and implemented in a timely fashion D


Correct Answer:

 

Question 28

Which one of the following answers shows two of the activities relating to tools that will take place during the transition stage of the service lifecycle?

A. Testing the tool and training process managers on using the process

B. Development or purchase of tools and deployment of the tools

C. Training tool administrators how to manage tools and monitoring tool performance in operational environment

D. Development or purchase of tools and deployment of the process

 


Correct Answer: AD

Question 29

Which process would seek to understand levels of customer satisfaction and communicate what action plans have been put in place to deal with dissatisfaction?

A. Availability management

B. Capacity management

C. Business relationship management

D. Service catalogue management

 


Correct Answer: C

Question 30

Which is the CORRECT activity to carry out the "How do we get there" phase of the Continual Service improvement approach?

A. Service and process improvement

B. Baseline assessments

C. Policy and governance review

D. Measurable targets

 


Correct Answer: A

Question 31

"Planning and managing the resources required to deploy a release into production" is a purpose of which part of the Service Lifecycle?

A. Service Operation

B. Service Strategy

C. Service Transition

D. Continual Service Improvement

 


Correct Answer: C

Question 32

Which of the following identifies the purpose of service transition planning and support?

A. Provide overall planning for service transitions and co-ordinate the resources they require

B. Ensure that all service transitions are properly authorized

C. Provide the resources to allow all infrastructure elements of a service transition to be recorded and tracked

D. To define testing scripts to ensure service transitions are unlikely to ever fail A


Correct Answer:

 

Question 33

Which statement about the `four Ps" of service design is CORRECT?

A. Processes refers to skills and training

B. Partners refers to suppliers and vendors

C. People refers to technology and tools

D. Products refers to procedures and metrics

 


Correct Answer: B

Question 34

Which of the following does the Availability Management process include?
(1) Ensuring services are able to meet availability targets
(2) Monitoring and reporting actual availability
(3) Improvement activities, to ensure that services continue to meet or exceed their availability goals

A. 1 only

B. All of the above

C. 1 and 2 only

D. 1 and 3 only

 


Correct Answer: B

Question 35

Which of the following are classed as stakeholders in service management?
1. Customers
2. Users
3. Suppliers

A. All of the above

B. 1 and 3 only

C. 1 and 2 only

D. 2 and 3 only

 


Correct Answer: A

Question 36

Which processes ensure the targets in the underpinning contracts are appropriate?

A. Design coordination and service level management

B. Supplier management and service level management

C. Service level management and availability management

D. configuration management and service portfolio management

 


Correct Answer: B

Question 37

Which of these would fall outside the scope of a typical service change management process?

A. A change to a contract with a supplier

B. A firmware upgrade to a server that is only used for IT Service Continuity purposes

C. An urgent need to replace a CPU to restore a service during an incident

D. A change to a business process that depends on IT Services

 


Correct Answer: D

Question 38

Which is the CORRECT list of metrics to support CSI activities?

A. Technology, customer and business

B. Business, service and technology

C. Customer, business and process

D. Process, technology and service

 


Correct Answer: D

Question 39

What are the categories of event described in the UIL service operation book?

A. Informational, scheduled, normal

B. Scheduled, unscheduled, emergency

C. Informational, warning, exception

D. Warning, reactive, proactive

 


Correct Answer: C

Question 40

Which process or function is responsible for monitoring activities and events in the IT infrastructure?

A. Service level management

B. IT operations management

C. Capacity management

D. Incident management

 


Correct Answer: B

Question 41

Which process is responsible for ensuring that appropriate testing takes place?

A. Knowledge management

B. Release and deployment management

C. Service asset and configuration management

D. Service level management

 


Correct Answer: B

Question 42

Which of these statements about Service Desk staff is CORRECT?

A. Service Desk staff should be recruited from people who have high levels of technical skill to minimize the cost of training them

B. The Service Desk can often be used as a stepping stone for staff to move into other more technical or supervisory roles

C. The Service Desk should try to have a high level of staff turnover as the training requirements are low and this helps to minimize salaries

D. Service Desk staff should be discouraged from applying for other roles as it is more cost effective to keep them in the role where they have been trained

 


Correct Answer: B

Question 43

The difference between service metrics and technology metrics is BEST described as?

A. Service metrics measure the end to end service; Technology metrics measure individual components

B. Service metrics measure maturity and cost; Technology metrics measure efficiency and effectiveness

C. Service metrics include critical success factors and Key Performance Indicators; Technology metrics include availability and capacity

D. Service metrics measure each of the service management processes; Technology metrics measure the infrastructure A


Correct Answer:

 

Question 44

Which of the following statement about the service owner is INCORRECT?

A. Carries out the day-to-day monitoring and operation of the service they own

B. Contributes to continual improvement affecting the service they own

C. Is a stakeholder in all of the IT processes which support the service they own

D. Is accountable for a specific service within an organization

 


Correct Answer: A

Question 45

Which of the following are benefits to the business of implementing Service Transition? (1) Ability to adapt quickly to new requirements
(2) Reduced cost to design new services
(3) Improved success in implementing changes

A. 1 and 2 only

B. 2 and 3 only

C. 1 and 3 only

D. None of the above

 


Correct Answer: C

Question 46

Which of the following activities would be performed by a process manager?
1. Monitoring and reporting on process performance
2. Identifying improvement opportunities
3. Appointing people to required roles

A. All of the above

B. 1 and 3 only

C. 1 and 2 only

D. 2 and 3 only

 


Correct Answer: A

Question 47

Which one of the following is the BEST description of a service level agreement (SLA)?

A. The part of a contract that speci es the responsibilities of each party

B. An agreement between the service provider and an internal organization

C. An agreement between a service provider and an external supplier

D. An agreement between the service provider and their customer

 


Correct Answer: D

Question 48

Which of the following processes contributes MOST to quantifying the financial value of IT services to the business?

A. Service level management

B. Financial management

C. Demand management

D. Risk management

 


Correct Answer: B

Question 49

Which is an example of how service automation assists service automation assists service management?

A. Customers can employ more sales staff during peak business periods

B. The capacity of services can be adjusted to respond to respond to variations in demand

C. Requests for new services can be authorized by anyone in service management

D. The capacity of the service desk can be reduced to prevent users contacting it at busy times

 


Correct Answer: B

Question 50

Contracts relating to an outsourced Data Centre would be managed by?

A. Service Desk

B. IT Operations Control

C. Technical Management

D. Facilities Management

 


Correct Answer: D

Free Access Full ITILF Practice Exam Free

Looking for additional practice? Click here to access a full set of ITILF practice exam free questions and continue building your skills across all exam domains.

Our question sets are updated regularly to ensure they stay aligned with the latest exam objectives—so be sure to visit often!

Good luck with your ITILF certification journey!

Share18Tweet11
Previous Post

Google Professional Cloud Security Engineer Practice Exam Free

Next Post

JN0-102 Practice Exam Free

Next Post

JN0-102 Practice Exam Free

JN0-103 Practice Exam Free

JN0-104 Practice Exam Free

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Recommended

Network+ Practice Test

Comptia Security+ Practice Test

A+ Certification Practice Test

Aws Cloud Practitioner Exam Questions

Aws Cloud Practitioner Practice Exam

Comptia A+ Practice Test

  • About
  • DMCA
  • Privacy & Policy
  • Contact

PracticeTestFree.com materials do not contain actual questions and answers from Cisco's Certification Exams. PracticeTestFree.com doesn't offer Real Microsoft Exam Questions. PracticeTestFree.com doesn't offer Real Amazon Exam Questions.

  • Login
  • Sign Up
No Result
View All Result
  • Quesions
    • Cisco
    • AWS
    • Microsoft
    • CompTIA
    • Google
    • ISACA
    • ECCouncil
    • F5
    • GIAC
    • ISC
    • Juniper
    • LPI
    • Oracle
    • Palo Alto Networks
    • PMI
    • RedHat
    • Salesforce
    • VMware
  • Courses
    • CCNA
    • ENCOR
    • VMware vSphere
  • Certificates

Welcome Back!

Login to your account below

Forgotten Password? Sign Up

Create New Account!

Fill the forms below to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.